BMC approves Rs. 10.25 crore plan to rebuild crumbling Mogra Nullah bridge
BMC approves Rs. 10.25 crore plan to rebuild crumbling Mogra Nullah bridge
Mumbai: BMC to Demolish and Reconstruct Vehicular Bridge Over Mogra Nullah
BMC approves Rs. 10.25 crore plan to rebuild crumbling Mogra Nullah bridge
The Brihanmumbai Municipal Corporation (BMC) is set to demolish and reconstruct the vehicular bridge over Mogra Nullah. Following a competitive bidding process, Ten Construction India Pvt Ltd has emerged as the lowest bidder, quoting 24.39% below the estimated cost. The total project cost, including all applicable taxes, is Rs. 10.25 crore. The proposal has been placed before the civic standing committee for final approval at its Wednesday meeting.
Structural Audit Findings
In 2022, the BMC undertook a structural survey of bridges in the western suburbs, appointing M/s SCG Consulting Services as the consultant. Their structural audit report submitted to the civic body revealed that the slab of the concerned vehicular bridge was in a severely deteriorated and unsafe condition. In view of the critical condition, the BMC decided to carry out a re-structural assessment of the bridge and appointed the Veermata Jijabai Technological Institute (VJTI) in 2024 for the purpose.
Following VJTI's re-evaluation, repair and rehabilitation of the bridge was recommended. The BMC invited bids, with nine companies participating; however, the lowest bidder quoted 24% below the estimated cost, raising concerns over work quality. The contractor's justification and rate analysis were examined by the technical consultant, who confirmed that the rates are reasonable, fair, and financially beneficial to the civic body. Accordingly, the proposal has been recommended for acceptance, subject to approval from the competent authority, said a civic official. The bridge work is expected to be completed within 12 months.
Key Specifications of the Bridge
- Length: 14.595 metres (including 3.5-metre approach roads on both sides)
- Width: 19.50 metres
- Foundation type: RCC pile foundation of 1200 mm diameter
- Structural type: Substructure comprising abutments and retaining walls with RCC deck slab supported on steel girders
- Superstructure type: RCC deck slab with steel girders.
Krasnodar's M4 Don Highway gets major safety upgrades and truck bans
A concrete barrier, new lanes, and weekend truck bans reshape one of Russia's busiest routes. Will these changes finally tame the chaotic M4 Don Highway?
S-Bahn closure sparks Leipzig-Halle car-sharing expansion for stranded commuters
No trains? No problem. A new car-sharing lifeline launches for 10,000 daily commuters facing months of rail chaos. Here's how it works—and what it costs.
Sydney's light rail near-misses expose deadly risks of distraction
One distracted step could be fatal. Shocking videos show how close pedestrians come to disaster on Sydney's light rail tracks.
Arizona Eyes an Autobahn-Style Highway with No Speed Limits
Could Arizona become the first U.S. state with an Autobahn-style highway? A bold bill aims to redefine speed limits—and spark debate on road safety.